Biogas-Plant/C3/Laying-the-foundation/English
|
Narration |
Slide Number 1
Laying the foundation of the Biogas plant |
Hello everyone.
Welcome to this Spoken Tutorial on Laying the foundation of the Biogas plant. |
Image of mason(s)
[[Image:]] |
This tutorial is particularly useful for masons. |
[[Image:]] | We are going to learn
How to construct a Biogas plant that-
|
To begin with we should know the following - | |
[[Image:]]
|
The Biogas plant consists of 3 different tanks -
|
[[Image:]]
[[Image:]] |
The standard dimensions of these tanks are as follows:
1. Mixing tank has a-
2. Gas holder dome has a-
3. The upper slurry tank has a-
4. The lower slurry tank has a-
|
Calendar
Day 1 Day 2 Day 3 |
For ease of understanding for the mason-
|
Animation
Day -1 |
Day -1 begins with digging of the area at the site of the Biogas plant. |
[[Image:]] | As shown here, use lime powder to mark the outline of-
Lime powder is easily available in any hardware store. |
[[Image:]] | Once the area is marked, start digging. |
[[Image:]]
Dimensions of image |
1. Dig a circular pit of 8 feet diameter and 4 feet depth using a shovel. 2. Just adjacent to the big pit, dig another pit of-
3. Two laborers can dig these pits in 2 days.
|
Graphic image:
Concave structure with dimensions |
The epicenter of the pit should be-
Effort should be made to keep the wall of the pit, as straight as possible. |
This completes the activities for Day 1.
Let’s move on to Day 2. | |
Animation | The activities of Day 2 are as follows -
|
In this tutorial, we will only learn about-
The other construction topics-
| |
So, now, we have completed the digging of the pit.
And we are ready to lay the foundation. | |
So, let us prepare the plaster mixture for the foundation. | |
The plaster mixture is basically the gravel and cement mixture. | |
[[Image:]] | Preparation of this mixture is as follows-
|
[[Image:]] |
|
[[Image:]] | Now pour this liquid over the dry gravel-cement mixture. |
[[Image:]] | Add adequate amount of water-
|
[[Image:]] | Use a shovel for mixing everything as shown in the image.
The gravel-cement mixture is now ready to be used. |
[[Image:]] | Use a small trowel to lay this mixture at the base of the pit, in a circular manner.
The thickness of the plaster should be 3 inches from the ground. |
|
This will form the floor of the pit.
|
[[Image:]] | Carefully raise the side walls of the pit upto 3 inches using the same mixture.
However, do not raise the concave part. |
[[Image:]]
[[Image:]] Arrows at the flattened raised edge |
Keep in mind-
|
|
After the foundation has been laid, leave it for curing for 12 hours. |
|
Notice the elevated walls and the concave pit, in the image shown.
Also, notice the flattened edges. |
With this, we complete this tutorial. | |
Slide 2
Summary In this tutorial we have learnt to: Lay foundation of the Biogas plant |
Let us summarize:
In this tutorial we have learnt to- Lay foundation of the Biogas plant. |
Slide 3
Acknowledgements This video was created by: Spoken Tutorial Project with inputs from Rural-ICT team, IIT Bombay. |
This video was created by-
Spoken Tutorial Project with inputs from Rural-ICT team, IIT Bombay. |
More information on these projects can be found at these links | More information on these projects can be found at these links. |
Pictures and technology support: Courtesy: Bhagirath Rural Development Foundation Village- Zarap, Taluka- Kudal, Dist.- Sindhudurg |
Pictures and technology support: Courtesy: Bhagirath Rural Development Foundation Village- Zarap, Taluka- Kudal, Dist.- Sindhudurg |
This is Bella Tony along with the animation team of the Spoken Tutorial project signing off.
Thank you for joining. |