Biogas-Plant/C2/Generation-of-Biogas/English-timed
From Script | Spoken-Tutorial
Revision as of 14:44, 25 November 2016 by PoojaMoolya (Talk | contribs)
Time | Narration |
00:01 | Hello Friends and welcome to the Spoken Tutorial on How to generate Biogas? |
00:08 | In this tutorial we will learn:When to add raw material to the Biogas plant. |
00:16 | Quantity of raw material to be added to the Biogas plant. |
00:23 | Use of slurry that is generated from the Biogas plant andBiogas burner and its connection process. |
00:35 | You will also see testimonial of Biogas users. |
00:42 | Recollect, an earlier tutorial that mentioned the raw materials to be added to the Biogas plant, which were Household food waste and Cow-dung |
00:58 | Cow-dung forms a favorable anaerobic environment for generation of Biogas. |
01:06 | So, when should the raw materials be added in the Biogas plant? |
01:12 | Once the civil work is over, the plant is left for curing for 17 days. On the 18th day, first load of raw materials can be fed into the plant. |
01:28 | As shown in this image Raw material should be fed into the mixing tank through the inlet pipe. |
01:38 | At this point, the important question is - How much raw material should be added to the Biogas plant? |
01:50 | The answer is-For the first time production of Biogas, add approximately 600 kgs of cow-dung. |
02:01 | And leave it for fermentation for 4 days. After 4 days, add at least 25 Kilograms of raw materials daily to the plant. |
02:18 | Along with this, add equal proportion of water.Which means a ratio of 1:1 has to be maintained. |
02:31 | For example, for 25 Kgs of raw material, 25 litres of water should be added. |
02:42 | Next, we will learn how to add the raw material into the inlet tank. |
02:51 | To add the raw material into the inlet tank- first, mix the raw material and water properly in the ratio of 1:1and then put this mixture into the feeding tank which is connected to the digester |
03:19 | Once the digester is completely filled with the mixture leave the plant for fermentation. |
03:30 | Note that, the time required for fermentation depends upon- The climatic conditions of the respective region Where the Biogas plant is set up |
03:47 | For eg. Fermentation in warmer regions will be quicker as compared to the cooler regions. |
04:00 | So, in warmer regions, leave the raw material in the digester tank for 4-5 days. |
04:13 | Once the fermentation is completed, two things happen simultaneously-Gas being lighter starts accumulating in the upper part of the dome. |
04:31 | and pressure generated by the gas, pushes the slurry outside. |
04:40 | The different ways to use this slurry are as follows: |
04:48 | It can be directly sent into the farms through drains. It can be manually poured into the nearby fields. |
05:03 | And it Can also be dried in drying pits to be used as dry manure. |
05:14 | Next, we will talk about choosing the right burner for using the Biogas. |
05:23 | The gas that is generated in the plant is conveyed through the main gas pipe.This main gas pipe should further be connected to an appropriate burner. |
05:42 | So which burner should be used? |
05:47 | The two types of burners available are- Biogas burner LPG burner |
05:58 | Please note, an LPG burner should not be used for Biogas. |
06:06 | The reason is LPG burners are specifically used for high compression LPG only. |
06:17 | Hence, LPG burners are not advisable for Biogas usage. |
06:26 | For using Biogas, it is best to buy a burner made of cast-iron due to its durability. |
06:37 | It is to be noted that -Like LPG stoves, Biogas stoves are also available in single and double burner models. |
06:50 | Single burner stove is of 8 cubic feet size |
06:55 | And Double burner stove is of 16 cubic feet size |
07:03 | So, where to procure Biogas burners from? |
07:09 | To buy the Biogas burner, one needs to contact the concerned-State Office of Khadi & Village Industries Commission also known as KVIC. |
07:25 | You can get the further contact details in the downloadable section.http://www.kvic.org.in/PDF/Right_to_Information.pdf |
07:33 | To confirm the generation of Biogas do the following. |
07:38 | Light the burner and check the flame for the Biogas. |
07:44 | The gas generated will be sufficient for the cooking needs of a family of 4-5 members. |
07:56 | Some Do’s and Dont’s for running a Biogas plant are- |
08:03 | On a daily basis Check flow of the waste from the Mixing tank into the Digester tank. Check that the slurry is flowing out of the slurry tank. |
08:19 | Do not keep the Mixing tank and Slurry tank uncovered. |
08:25 | Some safety measures to be followed when using the Biogas burner. |
08:32 | After every 4-5 days, drain out condensed water, if any In case gas is not going to be used for a long time, switch OFF the safety valve. |
08:50 | This will ensure that-The gas makes its way out from the outlet tank along with the slurry. |
09:00 | Now you will see Testimonial of some happy users. They will mention about- How convenient it is to use Biogas for cooking. |
09:11 | Which saves time, money and helps in improving health and hygiene |
09:21 | Hello,My name is Suresh Sahadev Manjrekar and this is my wife Supriya Suresh Manjrekar. We are a family of five people and we have 2 cows. |
09:44 | Every day I put 25kgs of cow dung mixed in equal quantity of water Into this mixing tank of the Biogas plant. I have also connected the toilet to the Biogas plant. |
10:07 | You can see the toilet just behind me. Using Biogas is very easy. It saves time and money. |
10:18 | Earlier I used to walk 25 minutes to collect firewood. Now I don’t go anywhere to collect firewood. Also, the slurry that comes out of the plant is collected in a pit which is 2-1/2 feet deep. |
10:42 | The slurry is then directed in a drain towards the fields I am very happy using Biogas |
10:54 | Let us summarize In this tutorial we have learnt-When to add raw material to the Biogas plant. Quantity of raw material to be added to the Biogas plant. |
11:11 | Different ways to use the slurry Different types of Biogas stoves.We also saw Testimonials from Biogas users |
11:25 | This video was created by-Spoken tutorial Project with inputs from Rural-ICT team, IIT Bombay. |
11:36 | More information on these projects can be found at these links.http://spoken-tutorial.org/NMEICT-Intro http://ruralict.cse.iitb.ac.in/ in |
11:42 | This is Bella Tony along with the animation team of the Spoken Tutorial project signing off.Thank you for joining. |