Time Narration
00:00 Hello. Welcome to this spoken tutorial on Material required to construct a biogas plant
00:09 In this tutorial, we will learn about the various materials required to construct a biogas plant
00:18 Area required to construct the plant
00:22 The Site, No. of days required for construction and the best time to construct the plant
00:32 Let us begin. The materials required to construct a biogas plant can be procured from any hardware & cement shop.
00:44 The following materials are required to construct the plant:
00:49 Cement 14 packs
00:51 Gravel – half brass
00:55 Sand - 1 brass
00:57 3 bundles of chicken mesh, 30 feet each
01:02 Weldmesh sheet of size 3 feet x 4 feet with 1 inch x 1 inch of the hole size
01:11 12 feet of 6 mm steel rods, 35kgs
01:18 1 kg of steel wire to be cut into 7-8 inches per piece
01:27 Bricks 3, 2kg of white cement
01:31 1 kg of lime powder
01:34 Jute gunny bags 25 Approximately
01:38 Plastic sheet- 13 feet x 10 feet and
01:43 7 Bamboo sticks of approximate size - 3.5 feet
01:49 Liquid waterproofing material - 1 Litre
01:53 Wooden square trowel with a concave bent from inside
01:58 These are especially used for smoothening the cement plaster on the dome of the Biogas plant
02:06 Metal square trowel
02:08 Shovel
02:09 Small trowel, Hook
02:12 Trough with a capacity of 10 kgs
02:16 Scissor to cut the chicken mesh
02:18 One Measuring tape
02:20 1kg of Newspaper
02:23 Scale with two hooves at the two ends and
02:28 An Iron rod with hollow ends at the either sides
02:33 We will now look at other items required to built the plant such as tubes, pipes and valves
02:45 We required main gas control valve of size 1 inch, metal pipe to be connected from the center of the dome, 30 cms x 1 inch of diameter
03:01 This will be the main gas pipe
03:04 Gas conveyer pipe of 1/2 inch diameter
03:08 The length of this pipe will depend upon the distance between Biogas plant and the kitchen
03:17 Inlet pipe connected from Mixing tank to Digester tank should be 6 inches diameter and approximately 5 feet of length
03:30 Another outlet pipe of 6 inches diameter to be connected from slurry tank to the slurry collection pit
03:39 If the outlet pipe is not required alternately, construct a drain between slurry tank and the slurry collection pit as shown
03:52 The depth of this slurry collection pit can be between 4 to 6 feet
04:00 The slurry collected in this pit can be manually poured in the fields
04:06 We also required a safety-valve of 1 inch
04:11 Approximately, 6 metres of rubber hose pipe of ½ inch diameter.
04:19 This rubber hose pipe will be used to convey the gas from the safety valve to the kitchen stove.
04:27 2 Vohj clips are require to secure the pipe.
04:32 A few other items like Synthetic Resin Adhesive 250 ml and Teflon tape
04:42 Always use good quality cement, gravel and sand.
04:48 These are really important for the durability of the biogas plant.
04:54 Let’s now talk about the- Area, Site, No. of days required for construction and best time to construct the plant
05:06 To construct the biogas plant, we need approximately 12feet X 8 feet of land, near the house.
05:16 The site should be such that construction cost is minimized and it receives ample sunlight to maintain the right temperature inside the biogas plant.
05:31 The selected site should also ensure easy operation and maintenance of Mixing tank, Digester tank, Main gas control valve to switch off gas inflow and the Slurry tank
05:49 The site should also be located near to the source of animal dung and the toilet.
05:57 This will help to easily operate the plant and avoid wastage of raw materials.
06:06 The total no. of days required to complete the civil work of a biogas plant are 3 to 5 days.
06:17 The best time of the year to construct the biogas plant is between November and June.
06:27 Constructing biogas plants during the rainy season is best avoided, as it becomes messy.
06:36 This brings us to the end of this tutorial on the material required to construct a Biogas plant.
06:45 The construction part of the Biogas plant will be explained in next tutorial under the same series
06:55 Let’s Summarize
06:57 In this tutorial, we learnt The material required to construct a biogas plant
07:06 Area required to construct the plant
07:09 Preferred site and
07:12 No. of days required along with the best time to construct the plant
07:19 This video was created by Spoken Tutorial Project with inputs from Rural-ICT team, IIT Bombay.
07:29 More information on these projects can be found at these links.
07:36 This is Bella Tony along with the animation team of the Spoken Tutorial project signing off.

Thank you for joining.

Contributors and Content Editors

PoojaMoolya, Pratik kamble, Sandhya.np14